THE FORCE MAJEURE CLAUSE AND ITS IMPACT ON CONTRACTS – Adv.Suyog Chandulal Shah 25/04/2020
The Force Majeure clause and its impact on contracts – Adv. Suyog Shah
COVID-19:
The Force Majeure clause and its impact on contracts
The global COVID-19 outbreak has disrupted all industries
and has put a significant population of the world under lockdown. This prevents
the efficient working of businesses and has impacted existing operations and
contracts. On the issue of contracts, this outbreak has brought many new
aspects to the fore, one of which includes the Force Majeure clause that
impacts formal contracts. Given the disruption of supply chains caused by the
COVID-19 pandemic, many contracts will be delayed, interrupted, or even
cancelled.
What
is Force Majeure?
As per the Manual for Procurement of Goods
2017, a Force Majeure means extraordinary events or circumstances beyond human
control such as an event described as an act of God (like a natural calamity)
or events such as a war, strikes, riots, crimes (but not including negligence
or wrong-doing, predictable/seasonal rain and any other events specifically
excluded in the clause).
A Force Majeure clause in the contract
frees both parties from contractual liability or obligation when prevented by
such events from fulfilling their obligations under the contract. This clause
does not excuse a party’s non-performance entirely, but only suspends it for
the duration of the Force Majeure. The firm has to give notice of Force Majeure
as soon as it occurs and it cannot be claimed ex-post facto.
There may be a Force Majeure situation
affecting the purchasing organization only. In such a situation, the purchasing
organization is to communicate with the supplier along similar lines as above
for further necessary action. If the performance in whole or in part or any
obligation under this contract is prevented or delayed by any reason of Force
Majeure for a period exceeding 90 (ninety) days, either party may, at its
option, terminate the contract without any financial repercussion on either
sides.
Notwithstanding the punitive provisions
contained in the contract for delay or breach of contract, the supplier would
not be liable for imposition of any such sanction so long as the delay and/ or
failure of the supplier in fulfilling its obligations under the contract is the
result of an event covered in the Force Majeure clause.
Is
COVID-19 considered under the Force Majeure clause in India?
The Ministry of Finance notification dated
19th Feb 2020, addresses this doubt and clarifies that the disruption of supply
chains due to the spread of corona virus should be considered as a case of
natural calamity and Force Majeure clause may be invoked, wherever considered
appropriate, following due procedures.
Invocation
of Force Majeure clause in Indian contracts
Many contracts may not contain the Force
Majeure clause explicitly to define clear execution/procedures to be conducted
to claim benefits under the clause due to the COVID-19 outbreak. Whether a
party can be excused from a contract on account of COVID-19 being declared a
pandemic is a fact-specific determination that will depend on the nature of the
party’s obligations and the specific terms of the contract. If the
contract does not include a Force Majeure clause, the affected party could
claim relief under the ‘Doctrine of Frustration’ under Section 56 of the Indian
Contract Act, 1872.
What is force majeure? The legal term everyone
should know during Covid-19 crisis
What is known to exist but is not visible is surrounded by mystery. It
excites the imagination and people spin yarns about it. Though that is not true
when it comes to novel coronavirus ("COVID-19"), the outbreak of which has been
globally reported. COVID-19 has caused worldwide unprecedented disruptions to
business operations; and the commercial turmoil continues. The pandemic has
impacted the ability of companies around the globe to maintain steady
operations and perform their respective contractual obligations.
Perhaps the companies in order to
mitigate the impact related to delayed operation and non-performance of the
contracts inter alia will take recourse to force majeure
clause contained in their contracts. An extraordinary event or circumstance
beyond human control such as event described as an act of God (like natural
calamity), government restrictions or other extraordinary circumstances which
prevent fulfillment of contractual obligations would qualify as a force majeure
event. This article, from the perspective of Indian Law, discusses the extent
of immunity offered by a force majeure clause and whether the said immunity can
still be claimed when there is no force majeure clause in the contact.
If Force Majeure clause is enshrined in the contract –
A classic force majeure clause would
require that the disruption of performance be beyond the invoking party's
reasonable control and that the event was not reasonably foreseeable. Whether
the COVID-19 would qualify a force majeure event will depend on each particular
contract i.e. the way force majeure clause has been worded in the
contract or what all contingencies have been captured (explicitly or impliedly)
in force majeure clause occurrence of which would qualify as a force majeure
event. The burden of proof rests on the party invoking the force majeure
clause. The said burden can be effortlessly discharged where force majeure
clause in the contract explicitly provides for events like epidemics, pandemics
or government restriction. However, the situation may become convoluted where a
force majeure clause is not explicitly worded and simply uses the term
"act of God" or "event beyond the reasonable control of
parties". Apart from this, a party's entitlement to the benefit of force
majeure clause would depend on the following factors:
Majority of contracts would require
the party invoking a force majeure clause to adequately appraise the
counterparty, within a stipulated time, regarding the event which prompted
invocation of force majeure clause. Further, the invoking party would be
expected to outline an estimation of the impact and duration of effects
resulting from the said event.
There is a possibility that parties
have an obligation to mitigate damages. In that case, what deserves
consideration is whether there are other means through which a party can
perform the contract or whether the party not affected by the force majeure
event is obligated to mitigate the damages in some way. Depending upon the
terms of a contract, the parties are expected to take reasonable steps.
Varied consequences of force majeure
event should also be considered. For instance, performance of the contract may
be suspended during the operation of force majeure event and performance may be
suitably extended, the parties may have option of renegotiating and modifying
the contract's terms or termination of contract would happen if the force
majeure event continues for specific period of time.
Nature of evidence on which the
claim of force majeure would be based is of utmost importance. It is vital that
the party invoking the force majeure clause must keep all documents related to
the force majeure event, which might be required in case a dispute arises in
future. In the present scenario, the said documents may include (i) national
and state government notice and guideline imposing restriction of trade, (ii) news
articles related to COVID-19 outbreak, quarantines, restricted travel and
mandatory shutdown of airports, trains stations and seaports, (iii) cargo
booking and freight agency agreement, (iv) cancelled flight or
train ticket or anything other documents relating to travel itinerary,
and (iv) cancelled visa or rejected visa application.
If contract does not have a Force Majeure clause –
This situation may appear, but the
same has been well guarded by doctrine of frustration prescribed under Section
56 of the Indian Contract Act, 1872 ("Act") and views adopted by the Hon'ble Supreme Court of India
since 1954. In a landmark judgment titled Energy watchdog Vs. Central Electricity Regulatory Commission reported
at 2017 (4) SCALE 580, Justice
R.F. Nariman of the Supreme Court opined that the event leading to
frustration which is relatable to an express or implied clause in a contract,
is governed by Section 32 of the Act and if it occurs the contract, it is
dealt with by a rule of positive law under Section 56 of the Act. Under the
prevailing circumstances, reliance on Section 54 of the Act depends upon the
following conditions: a valid and
subsisting contract between the parties; there must be some part of the
contract yet to be performed; and the contract after it is entered into becomes
impossible of performance i.e. subsequent impossibility.
It is imperative to mention that the
Indian Courts are according relief on account of subsequent impossibility when
it is found that the whole purpose or the basis of the contract has been frustrated
by the intrusion or occurrence of an unexpected event or change in
circumstances, which was not contemplated by the parties during execution of
the contract 1 or the performance of the contract becomes impracticable or
useless having regard to the object and purpose the parties had in view 2.
Apart from the above, the
initiatives taken by the Government of India deserve a special mention.
Government of India is taking necessary measures in order to prevent further
disruption in international trade and commerce by declaring outbreak of
COVID-19 as a force majeure event. For instance, Ministry of Finance issued an
office memorandum dated February 19, 2020 ("Memorandum") which
states that Force Majeure clause can be invoked in Government contracts if
there is a "disruption in supply
chain due to spread of corona virus in China or any other country".
The Memorandum further states that COVID-19 should be considered as a case of "natural calamity". Further
gaining strength from the Memorandum, the Ministry of New & Renewable
Energy has issued an Office Memorandum dated March 20, 2020 which directs all
Renewable Energy implementing agencies of the Ministry of New & Renewable Energy
(MNRE) to treat delay on account of disruption of the supply chains due to
spread of COVID-19 in China or any other country, as Force Majeure event.
Are we prepared for potential dispute in India?
Although currently it would be
impossible to ascertain the quantum and extent of damage caused due to the
outbreak of COVID-19, it would be prudent for any commercial organization to be
adequately prepared to protect their respective businesses from the prospective
disputes. Broadly, the following steps are accepted from a cautious business
house:
Promptly notify the counterparty
regarding the occurrence of a force majeure event, in the manner provided under
the contract.
Collate all documents related to the
force majeure event, as the same would serve as vital evidence at the time of
dispute resolution.
It is to be noted, in this context
that the Govt. of India Office Memo No.
F.18/4/2020 PPD dated 19-2-2020 issued by the Deputy Secretary to Govt. of India, Ministry of Finance states as
follows: “A doubt has arisen if the
disruption of the supply chains due to spread of corona virus in China or any
other country will be covered in force majeure clause. In this regard it is
clarified that it should be considered as a case of natural calamity and force
majeure clause may be invoked whenever considered appropriate, following the
due procedure.” Though this Office Memo gives government recognition to
COVID-19 as giving rise to force majeure in respect of the contracts dependent
on the supply chains, the courts may not apply the same principle for all
commercial contracts. The courts in India would rather go by aforesaid
principles and decide the cases on the basis of facts and clauses in each
contract. The courts will delve into whether the COVID-19 situation has
affected the fundamental basis of the contract. Recently, the Bombay High Court passed an ad-interim order on March 30,
2020 in the matter of Rural Fair Price Whoelsale Ltd. And Anr. v. IDBI
Trusteeship Services Ltd., IA No. 1/2020 in Commercial Suit No. 307/2020.
In the said case, the plaintiffs sought an injunction in respect of shares
pledged by them against the defendants. The plaintiffs submitted that an
outstanding loan payable to the defendants is near about Rupees 610 Crores.
Further, 8% of the equity shares are pledged with the defendants.
As on the date of the Debenture
Trust Deed, the market value per share was Rupees 350. It was submitted that
because of the present situation of COVID-19, the market has collapsed and on
1/3/2020, market value per share was below Rupees 303. It was submitted that
the defendants are fully secured and hence, they be restrained from taking any
steps for selling these shares in the market at present as in that event,
irreparable loss will be caused to the plaintiffs. The said submission was
opposed by the defendants stating that they have to recover more than Rupees
610 Crores and hence, relief should not be granted. The Court, taking note of the effect of COVID-19 on the market has
granted ad-interim protection and passed the restraining order against the
defendants.
HIGHLIGHTS
- A force majeure clause in a contract would typically include a list such as acts of God, war, terrorism, acts of government, fire, plagues.
- It also includes epidemics or a non- exhaustive list wherein the parties simply narrate what generally constitute force majeure events and thereafter add “and such other acts or events that are beyond the control of parties”.
- It would also include conditions which would have been fulfilled for such force majeure clause to apply to the contract.
- Clauses in a contract and the nature of the contract must be carefully ascertained.
- If there is a force majeure clause in the contract, inclusions and exclusions there from must be ascertained.
- If there is a mention of pandemics or epidemics in the force majeure clause (which is not commonly found), the present COVID-19 situation will definitely attract it. Section 32 of the Indian Contract Act relating to contingent contracts will support the same.
- If there is a clause in the contract which does not directly mention pandemics or epidemics, general words like ‘extraordinary events’ or ‘circumstances beyond reasonable control of the parties’ may be interpreted as attracting force majeure in COVID-19 situation.
- In the absence of any force majeure clause in the contract, Section 56 of the Indian Contract Act, making a provision of frustration of contract, will apply. This provision states that an agreement to do an act impossible in itself or which becomes impossible or unlawful later is void. However, where such a force majeure clause is present in the contract, Section 56 cannot be made applicable.
Conclusion –
The present COVID-19 situation may give rise to a lot of litigation in the corporate world, invoking the principle of force majeure. It will be therefore in the interest of the parties to renegotiate the contracts which are genuinely affected by COVID-19. The parties can after negotiation either terminate the contracts if found impossible of performance, or compensate a party if performance is extremely difficult, or accept suspension of the contract for certain period, or relax certain clauses in the contract.
Ensure a detailed evaluation of the contract and other related aspects by a legal expert.
At Adv.Suyog Shah
& Associates we have promptly and effectively transitioned to working
remotely. We are aware of the challenges our clients face as the businesses are
being impacted due to COVID-19 and are here to legally support during these
unprecedented times. Please feel free to reach us for any questions or concerns
you may have.We would like to assist you better for any kind of help and
Legal Assistance Kindly contact:-
Adv.Suyog Chandulal Shah
Adv.Suyog Shah & Associates,
Email :- advsuyogshah@gmail.com
Mobile No. 09850827178
Office No. 0253-2313178
Adv.Suyog Chandulal Shah
Adv.Suyog Shah & Associates,
Email :- advsuyogshah@gmail.com
Mobile No. 09850827178
Office No. 0253-2313178
Comments
Post a Comment